Enterprise Data Center to Cloud Migration
Role: Senior Solution Architect
Client: Certegy (Financial Services)
The Challenge
A major financial services company needed to migrate their entire data center infrastructure to AWS while maintaining strict compliance requirements and zero downtime for critical payment processing systems.
The Solution
- Designed hybrid cloud architecture with secure connectivity between on-premises and AWS
- Implemented phased migration strategy for 200+ applications across diverse technology stacks
- Built automated infrastructure provisioning with Terraform and CloudFormation
- Created comprehensive disaster recovery and failover procedures
Key Outcomes
Technologies Used
Project Overview
This enterprise-scale cloud migration involved moving a financial services company’s entire data center infrastructure to AWS. The project required meticulous planning to ensure compliance with financial regulations while maintaining zero downtime for critical payment processing systems.
Technical Approach
Phase 1: Assessment and Planning
We began with a comprehensive assessment of the existing infrastructure, cataloging over 200 applications and their dependencies. This phase included:
- Application dependency mapping
- Compliance requirement documentation
- Risk assessment and mitigation planning
- Migration wave planning
Phase 2: Foundation Building
The foundation phase established the core AWS infrastructure:
- Multi-AZ VPC design with proper subnet segmentation
- Transit Gateway for hybrid connectivity
- AWS Landing Zone implementation
- Security baseline and guardrails
Phase 3: Migration Execution
Migration waves were executed over 12 months, prioritizing applications based on:
- Business criticality
- Technical complexity
- Interdependencies
- Compliance requirements
Phase 4: Optimization
Post-migration optimization focused on:
- Right-sizing resources based on actual usage
- Implementing Reserved Instances for cost savings
- Performance tuning and monitoring enhancement
Key Learnings
- Start with the end in mind - Clear success criteria and rollback procedures are essential
- Communication is critical - Regular stakeholder updates prevented misaligned expectations
- Automate everything - Infrastructure as Code reduced errors and improved repeatability
- Test thoroughly - Comprehensive testing in lower environments prevented production issues